Weekly Executives Operation Meeting
VP Operation
September XX, 2025
Zoom Video Conference
PetroChina
2
9/23/2025
1
Drilling
2
Permit
3
CONTENTS OF REPORT
Jabung Operations Support
I. DRILLING OPERATION
3
9/23/2025
NO. | RIG | WELL | JOB SUMMARY | TIME AT WELL | FINISH DATE | HIGHLIGHT/REMARKS |
1. | RIG 26 (750 HP) | NEB-115 | Drilling | D+1 | | Current Activity: MIRU Next Activity: Spud In (Est. 02 Oct 2025) |
2. | RIG 86 (550 HP) | Gemah-32 | Well Service | D+1 | | Current Activity: MIRU Next Activity: Spud In (Est. 29 Oct 2025) |
3. | RIG 91 �(550 HP) | Gemah-16 | Well Service | D+3 | | Current Activity: MIRU Next Activity: Spud In (Est. 26 Oct 2025) |
I. DRILLING ENGINEERING SECTION
4
9/23/2025
NO. | Activities | Items Needing Immediate Attention | Proposed Solutions / Next Steps |
1. | Pre-Spud Meeting for Development Well NEB-115 | Finalize operational readiness before rig mobilization, including logistics, safety plans, and interdepartmental coordination | Complete all outstanding checklists and ensure readiness report is submitted to all relevant functions. Confirm rig and wellsite readiness |
2. | Submission of Panen-D11ST Well Operation Summary (Dry Hole Basis) to SKK Migas – Drilling Operations Section | SKK Migas requires insights into the well outcome and technical lessons learned | Ensure the formal report includes technical annexes (BHA summary, mud records, issue log) |
3. | Discussion with Subsurface Exploitation Team: Drilling Geohazard Identification Requirements for Upcoming Development Well SOR | Identification of geohazard risks (abnormal pressure, faults, shallow gas, etc.) for integration into SOR and Drilling Program | Finalize risk list, seek subsurface team confirmation (structure, pressure, fracture gradient), and integrate into SOR draft |
I. DRILLING LOGISTIC
5
9/23/2025
NO. | DESCRIPTION | WEEKLY ACTIVITIES/STATUS | NEXT STEPS |
1. | 027-BPA-D263-R - “Supply and Installation Services of Wellhead, Split Unihead and Christmas Tree” | Status : •IOM commercial evaluation is in progress by Procurement Dept. | •Procurement Dept. to finalize presentation for MC endorsement |
2. | 032-BPA-D263 - “Casing Low Grade 13-3/8” and 9-5/8” ” | Status : •Bid Plan Meeting with SKK Migas conducted on September 18, 2025 •Final assesment result and presentation from PT LAPI ITB | •Awaiting official tender invitation post-Bid Plan Meeting by Procurement Dept. |
3. | 033-BPA - “Tubing High Grade API Connection” | Status: •Bid Plan Meeting with SKK Migas conducted on September 18, 2025 | •Awaiting official tender invitation post-PQ process by Procurement Dept. |
4. | 034-BPA - “Tubing High Grade Premium Connection” | Status: •Bid Plan Meeting with SKK Migas conducted on September 18, 2025 | •Awaiting initiation of PQ process by Procurement Dept. |
5. | Long Term Contract (2 Years) for 7” High Grade Casing & 7” 13%CR Premium Connection Casing | Status: •Submit the proposal/CRS to the FPC Dept. for budgetary review on September 8, 2025. •Waiting the proposal/CRS review from FPC Dept. | •Awaiting FPC Dept. review outcome to proceed with CRS endorsement and tender preparation |
6. | 027-BPA-D263-R - “Supply and Installation Services of Wellhead, Split Unihead and Christmas Tree” | Status : •IOM commercial evaluation is in progress by Procurement Dept. | •Procurement Dept. to finalize presentation for MC endorsement |
I. DRILLING COST CONTROL
6
9/23/2025
NO. | WEEKLY JOB | HIGHLIGHT/REMARKS | |
I. | MONITORING AFE DRILLING & COMPLETION
| | |
| | ||
II. | CONTRACT EXPENDITURE REPORT (CER) Monitor, update and reconcile contract value absorption. | | |
III. | WEEKLY AFE MONITORING REPORT Prepare and submit Weekly AFE Monitoring report to Finance Dept as the cost references (AFE Development Wells) for PCI Financial Report. | | |
IV. | PERSETUJUAN PENYELESAIAN PEKERJAAN (P3) Waiting Pre-P3 Meeting result to continue to AFE COR Meeting. | | |
V. | ATB and INVOICING PROCESS Check, Prepare and Verify. |
| |
VI. | MONTHLY OVERHEAD CALCULATION Prepare and submit Monthly Overhead to Finance Dept for PCI Financial Report. | | |
I. DRILLING CONTRACT ADMIN
7
9/23/2025
NO. | CONTRACT NO. | DESCRIPTION | STATUS | ACTION | REMARKS |
1. | CRS NO. 005 | Wellview and Masterview for Subcription and Maintenance | Pending clarification from SCM Manager regarding TKDN and other subscription matters | MC Approval Meeting scheduled for 30 September 2025 | End-user (Drilling) to provide official response to SCM Manager's inquiries |
2. | PCJ-3712-CA | Workover Rig 350HP | Letter from PT. BDSI regarding Rig utilization (Rig 85 & Rig 91) has been requested; pending formal submission | Coordination with Legal Department has been completed; will proceed with IOM preparation upon letter receipt | Drilling Dept. to prepare IOM for internal approval once all supporting documents are received |
I. DRILLING SAFETY
8
9/23/2025
NO. | WEEKLY JOB | HIGHLIGHT/REMARKS |
1. | •H2S Management Services PCJ-3845-CA - PQ phase have been completed (Total 3 bidders PT ABI, PT SSH and PT Corroshield). Attachment 5 “Tender Plan Summary” has been reviewed and we are currently waiting for the remaining ITB documents from Procurement. | |
2. | Q3 Evaluation - All contractors have been evaluated: 9 under Drilling, 2 under EDS, and 4 under PE Department. | |
3. | Lesson Learned 2025 #12 – Socialization to all rig on Sept 24, 2025 | |
4. | ERP Well Control at Onshore Facilities – Internal QHSSE discussion planned for Friday, September 26, 2025. | |
5. | Finding Drilling Department MWT on July 31, 2025 – (BH #26: 19 Finding – BH #86: 13 Finding)
| |
I. DRILLING SAFETY
9
9/23/2025
NO. | WEEKLY JOB | HIGHLIGHT/REMARKS | |
6. | OSCP for Drilling Operation – The meeting regarding study progress has been completed. | | |
7. | Improvement of Safety Restraint, from King Safety Cable Model to Red Iron Sling Model (new) :
| Old Model | Old Model |