Weekly Executives Operation Meeting

VP Operation

September XX, 2025

Zoom Video Conference

PetroChina

2 of 9

2

9/23/2025

1

Drilling

2

Permit

3

CONTENTS OF REPORT

Jabung Operations Support

3 of 9

I. DRILLING OPERATION

3

9/23/2025

NO.

RIG

WELL

JOB SUMMARY

TIME AT WELL

FINISH DATE

HIGHLIGHT/REMARKS

1.

RIG 26 (750 HP)

NEB-115

Drilling

D+1

Current Activity:

MIRU

Next Activity:

Spud In (Est. 02 Oct 2025)

2.

RIG 86 (550 HP)

Gemah-32

Well Service

D+1

Current Activity:

MIRU

Next Activity:

Spud In (Est. 29 Oct 2025)

3.

RIG 91 �(550 HP)

Gemah-16

Well Service

D+3

Current Activity:

MIRU

Next Activity:

Spud In (Est. 26 Oct 2025)

4 of 9

I. DRILLING ENGINEERING SECTION

4

9/23/2025

NO.

Activities

Items Needing Immediate Attention

Proposed Solutions / Next Steps

1.

Pre-Spud Meeting for Development Well NEB-115

Finalize operational readiness before rig mobilization, including logistics, safety plans, and interdepartmental coordination

Complete all outstanding checklists and ensure readiness report is submitted to all relevant functions. Confirm rig and wellsite readiness

2.

Submission of Panen-D11ST Well Operation Summary (Dry Hole Basis) to SKK Migas – Drilling Operations Section

SKK Migas requires insights into the well outcome and technical lessons learned

Ensure the formal report includes technical annexes (BHA summary, mud records, issue log)

3.

Discussion with Subsurface Exploitation Team: Drilling Geohazard Identification Requirements for Upcoming Development Well SOR

Identification of geohazard risks (abnormal pressure, faults, shallow gas, etc.) for integration into SOR and Drilling Program

Finalize risk list, seek subsurface team confirmation (structure, pressure, fracture gradient), and integrate into SOR draft

5 of 9

I. DRILLING LOGISTIC

5

9/23/2025

NO.

DESCRIPTION

WEEKLY ACTIVITIES/STATUS

NEXT STEPS

1.

027-BPA-D263-R - “Supply and Installation Services of Wellhead, Split Unihead and Christmas Tree”

Status :

•IOM commercial evaluation is in progress by Procurement Dept.

•Procurement Dept. to finalize presentation for MC endorsement

2.

032-BPA-D263 - “Casing Low Grade 13-3/8” and 9-5/8” ”

Status :

•Bid Plan Meeting with SKK Migas conducted on September 18, 2025

•Final assesment result and presentation from PT LAPI ITB

•Awaiting official tender invitation post-Bid Plan Meeting by Procurement Dept.

3.

033-BPA - “Tubing High Grade API Connection”

Status:

•Bid Plan Meeting with SKK Migas conducted on September 18, 2025

•Awaiting official tender invitation post-PQ process by Procurement Dept.

4.

034-BPA - “Tubing High Grade Premium Connection”

Status:

•Bid Plan Meeting with SKK Migas conducted on September 18, 2025

•Awaiting initiation of PQ process by Procurement Dept.

5.

Long Term Contract (2 Years) for 7” High Grade Casing & 7” 13%CR Premium Connection Casing

Status:

•Submit the proposal/CRS to the FPC Dept. for budgetary review on September 8, 2025.

•Waiting the proposal/CRS review from FPC Dept.

•Awaiting FPC Dept. review outcome to proceed with CRS endorsement and tender preparation

6.

027-BPA-D263-R - “Supply and Installation Services of Wellhead, Split Unihead and Christmas Tree”

Status :

•IOM commercial evaluation is in progress by Procurement Dept.

•Procurement Dept. to finalize presentation for MC endorsement

6 of 9

I. DRILLING COST CONTROL

6

9/23/2025

NO.

WEEKLY JOB

HIGHLIGHT/REMARKS

I.

MONITORING AFE DRILLING & COMPLETION

  1. NEB-110 (Completion)
    • Operated by: Rig Bohai-86.
    • MIRU (Days): In total is meet with the planning.
    • Operation (Days): Exceeded by 9.52 days from the approved AFE
    • The estimated total expenditure is US$ 5,132,325 or under 17% from the approved AFE.

  1. Panen D-11ST (Drilling)
    • Operated by: Rig Bohai-26.
    • MIRU (Days): Under 1.08 days from the approved AFE
    • Operation (Days): Under 3.44 days from the approved AFE.
    • The estimated total expenditure is US$ 1,981,007 or under 63% from the approved AFE.

II.

CONTRACT EXPENDITURE REPORT (CER)

Monitor, update and reconcile contract value absorption.

III.

WEEKLY AFE MONITORING REPORT

Prepare and submit Weekly AFE Monitoring report to Finance Dept as the cost references (AFE Development Wells) for PCI Financial Report.

IV.

PERSETUJUAN PENYELESAIAN PEKERJAAN (P3)

Waiting Pre-P3 Meeting result to continue to AFE COR Meeting.

V.

ATB and INVOICING PROCESS

Check, Prepare and Verify.

  • ATB: 15 documents.
  • Invoice: 25 documents.

VI.

MONTHLY OVERHEAD CALCULATION

Prepare and submit Monthly Overhead to Finance Dept for PCI Financial Report.

7 of 9

I. DRILLING CONTRACT ADMIN

7

9/23/2025

NO.

CONTRACT NO.

DESCRIPTION

STATUS

ACTION

REMARKS

1.

CRS NO. 005

Wellview and Masterview for Subcription and Maintenance

Pending clarification from SCM Manager regarding TKDN and other subscription matters

MC Approval Meeting scheduled for 30 September 2025

End-user (Drilling) to provide official response to SCM Manager's inquiries

2.

PCJ-3712-CA

Workover Rig 350HP

Letter from PT. BDSI regarding Rig utilization (Rig 85 & Rig 91) has been requested; pending formal submission

Coordination with Legal Department has been completed; will proceed with IOM preparation upon letter receipt

Drilling Dept. to prepare IOM for internal approval once all supporting documents are received

8 of 9

I. DRILLING SAFETY

8

9/23/2025

NO.

WEEKLY JOB

HIGHLIGHT/REMARKS

1.

H2S Management Services PCJ-3845-CA - PQ phase have been completed (Total 3 bidders PT ABI, PT SSH and PT Corroshield). Attachment 5 “Tender Plan Summary” has been reviewed and we are currently waiting for the remaining ITB documents from Procurement.

2.

Q3 Evaluation - All contractors have been evaluated: 9 under Drilling, 2 under EDS, and 4 under PE Department.

3.

Lesson Learned 2025 #12 – Socialization to all rig on Sept 24, 2025

4.

ERP Well Control at Onshore Facilities – Internal QHSSE discussion planned for Friday, September 26, 2025.

5.

Finding Drilling Department MWT on July 31, 2025 – (BH #26: 19 Finding – BH #86: 13 Finding)

  1. Rig BOHAI #26, Closed 69%
  2. Rig BOHAI #86, Closed 100%

9 of 9

I. DRILLING SAFETY

9

9/23/2025

NO.

WEEKLY JOB

HIGHLIGHT/REMARKS

6.

OSCP for Drilling Operation – The meeting regarding study progress has been completed.

7.

Improvement of Safety Restraint, from King Safety Cable Model to Red Iron Sling Model (new) :

  • Rig-86: Closed
  • Rig-26: Open
  • Rig-91: Open

Old Model

Old Model