A street is supposed to be paved in a certain number of days. If the workers pave at the rate of 260m/day, the time of completion would have to be extended by 8 more days. If the workers pave at the rate of 300m/day, the time of completion would only have to be extended by 4 more days. How many days was the originally planned period?