PSPO Practice Test 3
80 câu hỏi, không giới hạn thời gian
Làm thêm tại https://khiemhuynh.com/kinh-nghiem-thi-psm
hoặc đọc thêm các bài viết về Agile, Scrum tại https://khiemhuynh.substack.com/ 
Email *
1. The purpose of Daily Scrums is for the developers to inform the Product Owner of the progress. *
1 point
2. There can be multiple Definitions of Done when multiple teams are working on the same product. *
1 point
3. Product Backlog only contains functional features, not non-functional features. *
1 point
4. Which of the following helps the Product Owner avoid waste in the project? *
1 point
5. What's the role of a Product Owner in composing the Sprint Goal? *
1 point
6. The Product Owner is not collaborating with the developers during the Sprint. What would you do as the Scrum Master? *
1 point
7. The Developers realizes that they have over-committed themselves for the Sprint. How should they review and adjust the work? *
1 point
8. No matter what we do, the customer doesn't provide enough user representatives for user acceptance testing during the Sprint. Who should try to fix this problem? *
1 point
9. The first Sprint can start as soon as the Product Backlog is complete. *
1 point
10. Adding new developers to the team may cause a short-term decrease in productivity. *
1 point
11. Which two of the following are time-boxed? *
1 point
Required
12. When multiple teams are working on the same product. The Sprints should start and end at the same time. *
1 point
13. What's the normal time-boxed duration of Sprint Planning when there are 6 developers in the team and Sprints are two weeks long? *
1 point
14. Which Scrum value is demonstrated when we continuously show the correct performance on a burn-down chart that everyone can see? *
1 point
15. Which two of the following actions may a Scrum Master take in starting up a project? *
1 point
Required
16. Which two statements best describe the Product Backlog? *
1 point
Required
17. What is a proper role of a PMO in a company that uses Scrum? *
1 point
18. Scrum Teams should normalize their estimations, so that management can measure and compare their performance. *
1 point
19. What is velocity? *
1 point
20. The Scrum Master can also be the Product Owner *
1 point
21. Which three of the following may be done in the Sprint Retrospective meeting? *
1 point
Required
22. Who owns the Sprint Backlog? *
1 point
23. Which two of the following are formal opportunities for inspecting and adapting? *
1 point
Required
24. Which two of the following can be used to reduce technical debt? *
1 point
Required
25. Sprint Review is a formal meeting. *
1 point
26. What are three benefits of having a Product Vision? *
1 point
Required
27. The Product Owner is responsible for composing the Definition of Ready. *
1 point
28. The Product Owner should determine how many items should be selected for the Sprint Backlog. *
1 point
29. Which of the following is LEAST likely to be used by a Scrum team? *
1 point
30. It's up to the self-organizing team to decide which Scrum events are needed in the project. *
1 point
31. Which two statements explain when a Product Backlog item is considered complete? *
1 point
Required
32. When does a Product Owner cancel a Sprint? *
1 point
33. How much time should a Product Owner spend with the developers? *
1 point
34. It's the end of the Sprint and an item doesn't meet what is defined in the Definition of Done. What are the two things we can do about this item? *
1 point
Required
35. Which two of the following can be reasons for the Scrum Master to attend the Daily Scrum? *
1 point
Required
36. The Developers is ready to start the first Sprint, but the Product Backlog is not ready yet. What should the Product Owner do? *
1 point
37. The Product Owner shouldn't allow the developers to start working without having the tasks identified and assigned. *
1 point
38. Some items in Sprint Backlogs are not directly about the features and functions of the product. *
1 point
39. The Developers cannot forecast how much work they can do in the upcoming Sprint because of uncertainties in the Product Backlog that the Product Owner is not able to overcome. What two actions should the Scrum Master recommend? *
1 point
Required
40. What do we do with Done items when the Sprint is canceled? *
1 point
41. What's the role of the Scrum Master during Sprint Retrospective? *
1 point
42. The Product Owner can allow the developers to create and add items to the Product Backlog. *
1 point
43. When do developers take ownership of a Sprint Backlog item? *
1 point
44. In scaled Scrum, each team demonstrates their individual Increment in a separate branch of the code. *
1 point
45. Which of the following may be done when the team becomes mature enough during the project? *
1 point
46. Which of the following is NOT required by Scrum? *
1 point
47. Which three of the following are typical things that a Product Owner does between Sprint Planning and Sprint Review? *
1 point
Required
48. The Sprint Backlog is base-lined at the end of Sprint Planning *
1 point
49. Which two of the following are correct about the Scrum Master role? *
1 point
Required
50. How often should the composition of the team change? *
1 point
51. Value can be determined only by revenue. *
1 point
52. Who decides when to release the product? *
1 point
53. Which of the following is needed for starting a new Sprint Planning? *
1 point
54. It's fine to have a PMO as long as it's focused on program management rather than direct involvement in Scrum projects. *
1 point
55. Teams A and B are working on two different projects. Team A has 8 members and a velocity of 600. Team B has 6 members+d a velocity of 500. Which team has a higher performance? *
1 point
56. Which of the following has the most to do with capturing and using lessons learned? *
1 point
57. Which of the following is a measure of success for the project? *
1 point
58. Which of the following best describes transparency? *
1 point
59. Daily Scrums are held at the same time and same place every day. *
1 point
60. Which two of the following should be considered in setting the time-boxed duration of Sprints? *
1 point
Required
61. How is the Product Backlog impacted by changes in the environment in which the product will be used? *
1 point
62. The satisfaction of which stakeholder has the highest priority? *
1 point
63. Which of the following may change during the Sprint? *
1 point
64. Items on the Sprint Backlog are average larger than those on the Product Backlog. *
1 point
65. The content of the Sprint Backlog emerges during the Sprint. *
1 point
66. Which of the following is a valid service from the Scrum Master to the Product Owner? *
1 point
67. Higher velocity = higher value *
1 point
68. How would you know if a Developers is cross-functional? *
1 point
69. Which two of the following can be considered real outputs of the Sprint? *
1 point
Required
70. The developers have difficulty understanding some of the items in the Sprint Backlog. What would you do as the Product Owner? *
1 point
71. Which two statements are correct about the Definition of Done? *
1 point
Required
72. Which two of the following are correct about Product Backlog Refinement? *
1 point
Required
73. There are no testers in Scrum. *
1 point
74. Which statement is correct about the Product Backlog? *
1 point
75. Who is responsible for engaging stakeholders? *
1 point
76. How much time is needed between a Sprint Retrospective and the next Sprint Planning to prepare the Product Backlog? *
1 point
77. Which of the following is not allowed in Scrum? *
1 point
78. Which of the following is the LEAST productive way for the Scrum Master to improve the Developers’s communications with the Product Owner? *
1 point
79. Scrum is a process for developing complex products. *
1 point
80. When is the Sprint Goal created? *
1 point
A copy of your responses will be emailed to .
Submit
Clear form
This content is neither created nor endorsed by Google. - Terms of Service - Privacy Policy

Does this form look suspicious? Report