Free PMP Quiz - Activity Duration Estimates
Quiz by Deep Fried Brain
Passing score is 60%.
Sign in to Google
to save your progress.
Learn more
* Indicates required question
Your name
*
Required
Your answer
Your location
Optional
Your answer
Your email address
Optional (enter if you wish to participate in the contest)
Your answer
Question 1
Project A and Project B have an expected duration of 48 days each. Their standard deviation is 4 days and 8 days respectively. What can you tell about the two project?
*
Project A is half as likely to complete on time as Project B
Project B is half as likely to complete on time as Project A
Project A has more risk than Project B
Project B has more risk than Project A
Question 2
Project A has an expected duration of 48 days and a standard deviation of 4 days. What is the probability of completing the project in 48 days?
*
100%
99.7%
95.5%
50%
Question 3
Project A has an expected duration of 48 days and a standard deviation of 4 days. What is the project duration estimate range?
*
44 days to 52 days
40 days to 56 days
36 days to 60 days
It cannot be determined with the given information
Question 4
Project A has an expected duration of 48 days and a standard deviation of 4 days. Your management wants to know the project duration estimate with a 95% confidence level? What estimate would you give them?
*
36 days to 60 days
40 days to 56 days
46 days to 50 days
36 days to 56 days
Question 5
Project A has an expected duration of 48 days and a standard deviation of 4 days. What is the probability of completing the project within 52 days?
*
99.7%
95.5%
84.1%
68.2%
Question 6
Project A has an expected duration of 48 days and a standard deviation of 4 days. What is the probability of completing the project between 48 days and 52 days?
*
2.1%
13.6%
34.1%
68.2%
Question 7
Project A has an expected duration of 48 days and a standard deviation of 4 days. What is the probability of completing the project within 44 days?
*
0.1%
2.1%
13.6%
15.9%
Question 8
Project A has an expected duration of 48 days and a standard deviation of 4 days. What is the probability that the project will take more than 60 days to complete?
*
0.1%
2.1%
13.6%
15.9%
Question 9
You are using PERT to determine the expected project duration. PERT assumes that activity completion time follows?
*
Free Distribution
Beta Distribution
Triangular Distribution
Normal Distribution
Question 10
An activity on the critical path has an expected duration of 10 days with a variance of 25 days. All of the following are potential options to reduce risks on the activity EXCEPT?
*
Fast-tracking the project
Outsourcing the activity
Eliminating the activity
Assigning an experienced resource to the activity
Quick Survey
How do you rate this quiz?
Easy
Just fine
Difficult
Clear selection
Would you like to see more such quizzes?
Yes
No
Clear selection
Submit
Clear form
Never submit passwords through Google Forms.
Forms
This content is neither created nor endorsed by Google.
Report Abuse
Terms of Service
Privacy Policy
Help and feedback
Contact form owner
Help Forms improve
Report