In Single resource scheduling, Shortest Processing Time (SPT) sequencing minimizes the
1 point
Clear selection
In single exponential smoothing, typically the value of α (alpha), the smoothing constant is selected in the range of
1 point
Clear selection
Critical path moves along the activities having the total float  of
1 point
Clear selection
Which one of the following does not form a part of the direct cost of component?
1 point
Clear selection
The artificial activity which indicates that an activity following it cannot be started unless the preceding activity is complete, is known as
1 point
Clear selection
Queuing theory is NOT used for
1 point
Clear selection
Match the Column – I with Column – II
2 points
Captionless Image
Clear selection
Seiketsu, a Japanese term of 5S methodologies, represents the method to
1 point
Clear selection
Continuous stock taking is a part of
1 point
Clear selection
In an economic order quantity based inventory control when re-order level is greater than order quantity, the number of orders outstanding at any time is  
1 point
Clear selection
7, 7, 7, 6, 6, 9, 8 and 6 are the times recorded for one element of operation. How many cycles are necessary for the time study? If the error is not to exceed 5% at the confidence level of 99.7%
2 points
Clear selection
In inventory planning, extra inventory is unnecessarily carried to the end of the planning period when using which of the following lot size decision policies?
1 point
Clear selection
In queuing theory, the ratio of the mean arrival rate and the mean service rate is called the
1 point
Clear selection
If the demand of an item is doubled and the ordering cost is halved, the economic order quantity (EOQ)
1 point
Clear selection
An airline has determined that 10 spare brake cylinders will give them stock out risk of 30%, whereas 14 will reduce the risk to 15% and 16 to 10%. It takes 3 months to receive items from supplier and the airline has an average of 4 cylinders per month. At what stock level should they reorder assuming that they wish to maintain 85% service level?
2 points
Clear selection
Monte-Carlo solutions in queuing theory are extremely used in queuing problems
1 point
Clear selection
A company sells 14,000 units of its product. It has variable cost of Rs.15 per unit. Fixed cost is Rs.47,000 and the required profit is Rs.23,000. Per unit product price (in Rs.) will be
1 point
Clear selection
Which of the following is NOT advantage of Master Scheduling?
1 point
Clear selection
In M/M/1 queue, the arrival rate is
1 point
Clear selection
In an assembly line for assembling toys, five workers are assigned task which times of 10, 8, 6, 9 and 10 minutes respectively. The balance delay for line is
2 points
Clear selection
If at optimum in a linear programming problem a dual variable corresponding to a particular primal constraint is zero, then it means that  
1 point
Clear selection
If R is the base rate guaranteed per hour, S is the standard time for the job and T is the actual time, then wages for the job will be, according to Halsey 50-50 plan and Rowan plan  
1 point
Clear selection
Both Rowan plan and 50-50 Halsey plan will provide same earning when the actual time is ______ the standard time.
1 point
Clear selection
Chart which is useful for scheduling and control is