HCP SOP Training Questionnaire
Email *
Name of Test Taker *
What should the copper sulphate rod sponge be kept in before the test? *
10 points
What phase of electricity should be obtained at site? *
10 points
Multimeter should be set at what setting? *
10 points
Arrange the following steps in the correct order
*
Choose the option with the correct order
10 points
Which step is missing in the following chain of events?
*
1. Attachment must be made directly to the reinforcing steel except in cases where it can be documented that an exposed steel member is directly attached to the reinforcing steel.
2. ?
3. Measure voltage in millivolts.
10 points
When should you pre-wet the concrete surface? *
10 points
How long should the reading remain stable after pre-wetting the concrete surface? *
10 points
Where should the test be repeated? *
10 points