Plan To Build 3 Elementary Schools, EE Smith, and an
Addition at Grays Creek High School

School Year 26-27

FROM

TO

Douglas Byrd North

Douglas Byrd Middle South

Cumberland Virtual Academy

71st
High School

AB Wilkins

Douglas Byrd Middle North

Manchester

WT Brown/Ponderosa

EC Staff

TC Berrien (after CVA vacates)

Ramsey Street

Pauline Jones

JW Coon

Sherwood Park/Brentwood

  • Design and Preliminary Work - JW Coon Site
  • Design and Preliminary Work - EE Smith Site
  • Prepare Reid Ross to receive EE Smith students as swing space

School Year 27-28

FROM

TO

Anne Chesnutt

Lewis Chapel/Westover

Reid Ross Middle

Nick Jeralds/71st Classical for those that want to remain classical - no transportation provided

Reid Ross High

  • Massey Hill for those that want to remain in classical setting - no transportation provided
  • Students that want to attend EE Smith will stay at Reid Ross because this is the swing space for EE Smith

EE Smith

Reid Ross (Swing Space)

  • Start construction on the new JW Coon Building
  • Finish design around December 27 and Break ground early January of 2028 at EE Smith Building (based on a June/July Design starting point)
  • Begin design and preliminary work - Ferguson-Easley Site
  • Update AB Wilkins to accept Ferguson-Easley students as a swing space

School Year 28-29

  • Continue construction on new JW Coon building
  • Continue construction on new EE Smith building
  • Begin design and preliminary work on Stedman site
  • Finalize design and preliminary work on Ferguson-Easley site

School Year 29-30

FROM

TO

Sherwood Park/Brentwood

New JW Coon building

Ferguson-Easley

AB Wilkins (Swing Space)

  • Start construction on new Ferguson-Easley building
  • Start construction on new Stedman building
  • Continue construction on new EE Smith building
  • Start Design on Gray’s Creek addition

School Year 30-31

FROM

TO

Reid Ross

New EE Smith building

  • Continue construction on new Ferguson-Easley building
  • Continue construction on new Stedman building
  • Start construction on Gray's Creek addition

School Year 31-32

FROM

TO

Stedman Primary/Stedman Elementary

New Stedman building

AB Wilkins/Margaret Willis

New Ferguson-Easley Building

  • Provide AB Wilkins to the county
  • Use Gray's Creek addition