Plan To Build 3 Elementary Schools, EE Smith, and an
Addition at Grays Creek High School
School Year 26-27
FROM | TO |
Douglas Byrd North | Douglas Byrd Middle South |
Cumberland Virtual Academy | 71st High School |
AB Wilkins | Douglas Byrd Middle North |
Manchester | WT Brown/Ponderosa |
EC Staff | TC Berrien (after CVA vacates) |
Ramsey Street | Pauline Jones |
JW Coon | Sherwood Park/Brentwood |
- Design and Preliminary Work - JW Coon Site
- Design and Preliminary Work - EE Smith Site
- Prepare Reid Ross to receive EE Smith students as swing space
School Year 27-28
FROM | TO |
Anne Chesnutt | Lewis Chapel/Westover |
Reid Ross Middle | Nick Jeralds/71st Classical for those that want to remain classical - no transportation provided |
Reid Ross High | - Massey Hill for those that want to remain in classical setting - no transportation provided
- Students that want to attend EE Smith will stay at Reid Ross because this is the swing space for EE Smith
|
EE Smith | Reid Ross (Swing Space) |
- Start construction on the new JW Coon Building
- Finish design around December 27 and Break ground early January of 2028 at EE Smith Building (based on a June/July Design starting point)
- Begin design and preliminary work - Ferguson-Easley Site
- Update AB Wilkins to accept Ferguson-Easley students as a swing space
School Year 28-29
- Continue construction on new JW Coon building
- Continue construction on new EE Smith building
- Begin design and preliminary work on Stedman site
- Finalize design and preliminary work on Ferguson-Easley site
School Year 29-30
FROM | TO |
Sherwood Park/Brentwood | New JW Coon building |
Ferguson-Easley | AB Wilkins (Swing Space) |
- Start construction on new Ferguson-Easley building
- Start construction on new Stedman building
- Continue construction on new EE Smith building
- Start Design on Gray’s Creek addition
School Year 30-31
FROM | TO |
Reid Ross | New EE Smith building |
- Continue construction on new Ferguson-Easley building
- Continue construction on new Stedman building
- Start construction on Gray's Creek addition
School Year 31-32
FROM | TO |
Stedman Primary/Stedman Elementary | New Stedman building |
AB Wilkins/Margaret Willis | New Ferguson-Easley Building |
- Provide AB Wilkins to the county
- Use Gray's Creek addition