Authored By:  Douglas “Mitch” Mitchell

Contributions By:  Jackie Duty

June 10, 2003


Summary


Moving (expanding/remodeling) data centers, server farms, software development labs and test labs with minimum disruption to end-users requires precision planning and execution skills.  It is one of the most challenging single event projects an IT department can take on.  These relocations include all aspects of the IT environment including facility construction, power, HVAC, networking, security, servers, storage, databases, applications, Internet services and data center operations.  Poorly planned relocations have resulted in the demise of many project managers.

To survive you must know what you have to relocate, how it works and interfaces with other components, be able to design the new data center layout, perform the many layers of planning necessary, interface with all the external points of contact, execute the move and then deal with any resulting problems.

These data center moves are a rare event in the life of an IT department, requiring many special skills, across multiple disciplines.  It is not the kind of project where move planning is done in one’s spare time and the move is done over a weekend.  Moving a data center using this approach is very high risk. The reality is that planning and moving a data center is a very complex project with many potential points of failure.  Since these are rare events and many disciplines are involved in the planning and execution of a Data Center Relocation, the internal staffs simply do not have actual experience with or exposure to this type of work.  Ideally, you need to engage someone with the project management skills, technical expertise, as well as experience in the individual IT disciplines to be successful in data center relocations.

This paper provides tips and tricks on data center relocations and expansions.  It is not intended to be a complete blue print on how to relocate data centers.  Some concepts may seem like mother hood and apple pie but it is surprising how many times they are not followed resulting in problems and schedule delays.  For more detail or help in relocating your data center please contact the author of this paper.



Relocation Approaches


The relocation approach selected depends on business strategies, requirements, cost constraints and acceptable business risks.  These business directions are critical in selecting the most appropriate relocation approach.  Once the approach has been defined the team can proceed with developing the relocation approach, analyze the current environment and develop a plan for the relocation.  Following are the basic approaches used for these relocations.

Note:  If at all possible, pre-install and test all network components well ahead of the move.



Safety First


People’s safety should be the number one priority.  Data Centers have many safety hazards including heavy equipment, talk racks, high voltage electricity, holes in the floor and many sharp edges. Nothing can ruin relocation faster then someone injured or worse.


Analysis


As with any project, the first phase is to develop an analysis of why you are doing it, what you are dealing with and what the expectations are of all parties impacted by the relocation.  


Planning


Planning is a key data center relocation element.  It includes all aspects of the relocation including communication, organization, task plans and testing.  Without a detailed plan the relocation has little chance of succeeding.  


Teams


The relocation team is critical to the success of the relocation.  They need to be comprised of the right resources, to be well informed and work together to ensure the success of the relocation.


Transportation


The actual move of the equipment and data can make or break data center relocation.  If the equipment and or data does not reach the new site on schedule and in one piece the relocation will be a failure.  All necessary precautions need to be covered so that the equipment and backups arrive in tact and on schedule.



Facility


There are many facility aspects associated with a Data Center Relocation including construction, remodeling, layout, power, security, environmental controls and fire suppression.  All of these are required to be completed and tested before the actual move.  In general they need to be done by professionals who are experienced in working with data centers.  But, their work still needs to be overseen by the Data Center Relocation team as what they do and their timing directly affects the schedule and success of the data center relocation.



Testing


Follow the standard testing processes of unit testing, system testing and acceptance testing.

 



Communications


Effective communications are essential to a successful Data Center relocation effort.  The Communications Plan needs to address requirements for the internal move team and all affected stake holders including:

Relocating a data center is a major undertaking.  But, circumstance may require that it must be done.  With enough analysis, planning, a good contingency plan and a strong team, you can relocate your data center with minimum disruption of service and avoid unexpected down time and data loss.

Copyright by Douglas Mitchell © June, 2003 - Data Center Relocation Tips & Tricks

www.douglas-mitchell.com        

Page  of