Status Report as of: 11/14/25

Project Health

Project Phase

Target Completion Date

Green (On Track)

Build & Manage

07/10/2026

Why is the Project’s Status “Yellow (At Risk)” or “Red

Milestone

Date

Status

2020 Climate Plan Review Complete

08/2025

Completed

2025 Climate Plan Outline

09/2025

Completed

Initial Draft Review w/Implementation Committee

10/2025

In Progress

Secondary Draft Review w/Whole Campus Committee

11/2025

Not Started

Cabinet Review

11/2025

Not Started

Draft for Public Review

12/2025

Not Started

Final Climate Action Review sent to UCOP

06/2026

Not Started