Contractor HSE Management

Process Quick Guide

Step 1 – Defining the Scope of Work

Action Required By the Service Requestor / Project Manager:

Tier 1

Tier 2

Develop a scope of work that that explains / highlights:

  • Overview (description, size, location, phases, contact and payment information, selection process, standards and regulations
  • Deliverables (objectives, timelines, milestones, designs, labor, material)
  • Considerations (monitoring, evaluation, specific and related tasks, critical tasks, hazards/controls and associated risk levels)

Required

Required

Submit the completed scope of work to the SCM department for review and action

Required

Required

The value of this task is:

  • Contractors are qualified for the expertise and pricing of the scope
  • Timelines and deliverable are clear and can be compensated accordingly

Step 2 – Communicating and Establishing Contractor HSE Expectations

Action Required By SCM:

Tier 1

Tier 2

Provide potential service providers with the following information:

Required

Required

Action Required By The Potential Service Providers:

Tier 1

Tier 2

Review the following information:

  • Ensure the following sections are reviewed in detail … to ensure alignment to expectations
  • Pre-Qualification form (HSE portion estimated 30 min one time) – Step 3
  • Kick Off Meeting form (JACOS  to complete, estimated 60 min one time during meeting) – Step 4
  • Site Access Request forms and associated training requirements (estimated 5 mins to complete) – Step 5
  • Monthly Stewardship form (estimated 30 min monthly) – Step 5
  • HSE Performance Evaluation form (JACOS  to complete, estimated 30 min) – Step 6

Required

Required

The value of this task is:

  • To provide current and clear HSE governance and associated expectations to ensure it is built into the any work plans

Step 3 – Contractor Pre-Qualification

Action Required By SCM:

Tier 1

Tier 2

Provide potential service providers with the Prequalification Form and assess / rank upon return

Required

Optional

Action Required By The Potential Service Providers:

Tier 1

Tier 2

Complete the Pre-Qualification Form and submit all required documentation back to SCM

Required

Optional

The value of this task is:

  • To review and assess Potential Service Providers against each other and industry to ensure diligence during the selection process

Step 4 – Selection and Development of Appropriate Agreement

Action Required By SCM and/or Service Requestor / Project Manager:

Tier 1

Tier 2

Communicate to the Potential Service Provider their success and schedule a kick-off meeting

Required

Optional

Re-Communicate Site Access requirements 

Required

Required

Connect the Service Provider with kaleena.carriere@jacos.com email and provide them with the “Welcome To Camp Package” 

Required

Required

Action Required By Service Requestor and Identified Service Providers:

Tier 1

Tier 2

Review and ensure all of the items from the Kick off check list have been reviewed and completed if appropriate.

NOTE: The JACOS HSE Team is a resource that can help explain and translate all the expectations within this list if required

Required

Optional

Hold / Attend the Kick Off Meeting

Required

Optional

The value of this task is:

  • To minimize the delays and learning curves that might be created during mobilization

Step 5 – Contractor Management and Performance Tracking

Action Required By The Service Requestor:

Tier 1

Tier 2

Mobilize workers to site using the Site Access Form 

Required

Required

Manually track non-swipe exposure hours and submit to rebecca.rankin@jacos.com if a Monthly Stewardship Report is not being completed before or on the 4th working day of every month (while conducting work)

Not Required

Required if not completing Monthly Stewardship Report

Action Required By The Identified Service Providers:

Tier 1

Tier 2

Ensure all workers have the required Site Access Training and are competent to perform all required work

Required

Required

Complete the Monthly Stewardship for and send to rebecca.rankin@jacos.com and your Service Requestor before or on the 4th working day of every month (while conducting work)

Required

Optional

The value of this task is:

  • To minimize the delays and learning curves that might be created during mobilization
  • To monitor and assess onsite performance and steward it accordingly
  • Provide data in a timely manner that is required for the JACOS HSE Monthly Reports

Step 6 – HSE Performance Evaluation

Action Required By The JACOS HSE Team:

Tier 1

Tier 2

Complete the HSE Performance Evaluation and forward off to the Service Requestor for signoff

Required

Required

The value of this task is:

  • To assess and store Service Providers onsite performances to later review during the awarding of new scopes of future work.

© Japan Canada Oil Sands Limited