Derrick A. Burnett 443.985.0742 C4bmore1@gmail.com
Summary
- Have 25 years of design & construction industry experience, including the Renewable Energy Design and construction industry, Federal government and Military sector.
- As Site Superintendent, I've been responsible for the supervision and overall management of the job site, including the on-site coordination of subcontractors to meet all schedule milestones.
- Have expertise in construction oversight, with knowledge of Electrical, HVAC, fire protection systems, communication / security systems, building envelope and construction methodologies.
- Well-versed in coordinating multi-disciplinary teams, including Mechanical Electrical and Plumbing Contractors
- I am an effective communicator with a proven ability to quickly identify risks and offer solutions. A highly experienced superintendent with extensive project manager experience.
- Have an in-depth understanding of issues such as OSHA 30 Safety Criteria, Subcontractor Coordination, Business Development, Design and Construction Code, Compliance Criteria, Design & Constructability Reviews, Submittals, Project Closeout.
Certifications:
- Construction Quality Management – (USACE / NAVFAC - CQM)
- (U.S. Army Corps of Engineers-NAVFAC-Certification)
- ASHE Healthcare Construction Certificate
- Design Build Institute- Albuquerque NM
Design Build – Project Delivery
Design Build- Contract & Risk Management
- Construction Specifications Institute - Austin, TX
OSHA 30- 360 Training,
Education:
Harvard University- Cambridge Mass.
- Advance Architectural Delineation
Johns Hopkins University- Baltimore, MD
American Institute of Architects- Hampton University - Hampton VA 23688
- Bachelors of Architecture 5 year professionally Accredited Degree
Professional Experience
University of Maryland Planning & Construction June 2024 to Jan 2025
MLK Communications, Arts and Humanities Building
Sr. Project Manager (*Simultaneously with other BSU Projects)
- Managed an of site project at Bowie State University, 192,000 square feet
- $159 Million dollar building, substantial completion August 2024,
- *Implemented Maryland Green Building Council’s High Performance Green Building Program.
- *Design Features: 1500 seat auditorium and production facilities for the University’s radio and television stations that support student productions. (2) Tiered Classrooms 150 seats each. 18 Active Learning can collaborative Instructional spaces. Recording studios and Screening room.
Completed the last construction phase of the building, executed and managed the associated $3 million-dollar Interior furniture installation.
- Maintained & Reviewed Project Budget and Change Orders
- Attended & Document Design & Construction Project Meetings
- Monitored Construction quality & ensure Adherence to Design Standards & Criteria
- Managed punch list and building turnover process.
- Coordinated and verified as-built drawings and Operations and Warranty Manuals
- Documented and addressed issues during Post occupancy and warranty reviews.
- Oversaw Commissioning Plans and processes to complete the project.
Bowie State University Charlotte Robinson Building- Interior Renovation Project 33,000. Sq.ft.
Sr. Project Manager (*Simultaneously with other BSU Projects)
- Managed the final renovation components of the interior spaces, exterior window
- storefront replacements and upgraded HVAC and Lighting control systems. Using the Design Build Construction Management System & the Guaranteed Maximum Price Contract.
- Maintained & Reviewed Project Budget and Change Orders Attended & Document Design & Construction Project Meetings
- Monitored Construction quality & ensure Adherence to Design standards & criteria
- Managed punch list and building turnover process.
- Coordinated and verified as-built drawings, operations and Warranty Manuals
- Documented and addressed issues during post occupancy and warranty
- Oversaw Commissioning Plans and processes to complete the project.
Bowie State University Harriet Tubman Residential Building – Interior Renovation project 33,000 sq. ft. $10.5 Million Dollar Project (*Simultaneously with other BSU Projects)
Sr. Project Manager
- Initiated the complete renovation of the oldest building on the Campus of Bowie State University (1921), using the Design Build Construction Management System & the Guaranteed Maximum Price Contract.
- Participated in the selection of the Design Build Construction team.
- Coordinate with the design team to meet the client’s design guidelines and criteria.
- Initiated the building assessment and survey process of existing hazardous waste and utilities infrastructure with the design build team subcontractors, and BSU onsite engineering discipline representatives. Initiated the
- Schematic design and preliminary construction estimate submission process
- Participated in bi-weekly onsite and virtual project meetings representing UMD planning & Construction division, with the design build contractor and the Bowie State University representatives.
Hanna Solar GS -Ft. Belvoir North Area, Arlington VA Mar 2024 to April 2024
Project Manager
- Tooele Army Depot Base, Tooele, UT - Provided Closeout services on a $8 million-dollar 1.5 -Megawatt Solar System 3100 panel Solar System Inclusive of 485 watt Hanwah Solar panels, 12 Inverters inside a stand-alone 1200 sq. ft. metal building, inclusive of 13 single mode and 13 multimode fiber optic network communication and security system. Collaborated with Engineers, Electricians, Solar Technicians, Laborers, Fiber Optic installation and testing personnel.
- Attended & Documented Design & Construction Project Meetings
- Monitored Construction quality to design standards & criteria
- Managed punch list and building turnover process.
- Coordinated and verified as-built drawings and Operations and Warranty
- Documented and addressed issues during post occupancy and warranty reviews.
- Managed commissioning documentation and project closeout.
- Oversaw Commissioning Plans and processes to complete the project.
Hanna Solar GS -Ft. Belvoir North Area, Arlington VA
Site Superintendent Jan 2024 to April 2024
- $9 Million Dollar -North Area Distribution Center - 525,000 sq. ft. distribution center - Rooftop Solar Panels on a High Bay Warehouse Facility, inclusive of a 450 Space Carport Solar System.
- Attend & Document Design & Construction Project Meetings
StrucSure - Aberdeen Proving Grounds - Edgewood, MD Aug 2023 to Dec 2023
USARMCI - United States Army Medical Chemical Institute
Site Superintendent/Contractor
- Animal Lighting and HVAC Upgrade project.
- Attend & Document Design & Construction Project Meetings
- Monitor Construction quality & ensure Adherence to Design Standards & Criteria
- Managed punch list and building turnover process.
- Coordinated and verified as-built drawings and Operations and Warranty Manuals
- Documented and addressed issues during Post occupancy and warranty reviews.
- Managed commissioning documentation and project closeout.
- Oversaw Commissioning Plans and processes to complete the project.
Derrick A. Burnett 443.985.0742 C4bmore1@gmail.com
Planate Mgmt - Veterans Administration Hospital- Perry Point, MD Sept 2022 to June 2023
EHRM-Electronic Health Records Maintenance & Telecommunication Upgrade –$33 Million Dollar Project.
- Generated Scope of Work, Construction Project Development Schedule and generated construction estimate for a 40 Building 400 Acre Hospital Campus, to implement the new Veterans Administration Hospital Wide EHRM-Electronic Health Records Maintenance & Telecommunications Upgrade. Reviewed 20 A&E Firms RFP Submissions for Qualifications, Past Performance and Capabilities.
USACE Design & Engineering Division Baltimore District
- Executed Design Reviews According to USACE Design Criteria, & Implemented Value Engineering Review Projects, over 1,000,000 Sq. Ft.
USARNG Headquarters Alexandria, VA
Engineering Consultant
- Design & Construction Criteria Review Projects ($1.2 Billion dollars in projects for the United States Army National Guard Sites Throughout North America)
MDANG Middle River MD 235th CEF
Civil Engineering Flight (Captain)
- Designed & Constructed projects in (5) different countries throughout the world. (England, Spain, Iceland, South America (PERU) and Portugal.
USACE - Project Architect- GS-808/12 Baltimore District Army Corps of Engineers-Design Branch- Baltimore, MD
Project Architect -Ft. Meade, MD
- Defense Information School (230,000 sf; $30 million BRAC - Base Relocation and Closure Project -Combined 5 Military Journalism Schools into one facility and location, while interacting with representatives from all branches of the Military throughout the country)
Project Architect Ft. Meade, MD
- Operations Training Facility
Project Architect Ft. Belvoir, VA
- 300 Staff interior Design Space Planning
GreenBrilliance Washington DC-Baltimore Area Mar 2021 to Feb 2024
3 yrs Commission Sales Associates - Part-time
AEI -Design Build LLC. Jan 2012 to May 2024
General Contractor - Project Manager
Johns Hopkins Hospital - Baltimore, MD
- Cancer Center Interior Renovation (Subcontractor- Russell Construction)
Johns Hopkins Hospital - Baltimore, MD
- Cafeteria Renovation (Subcontractor Russell Construction)
Department of Veterans Affairs - Baltimore, MD
- Housing and HISA-Home Improvement and Structural Alterations ADA-Accessibility Upgrades Program
First Baptist Church of Guilford - Columbia, MD
- 12,000 sq. ft. Addition - Design Build Project Manager $7,000,000.00
New Shiloh Baptist Church - Baltimore, MD
- Family Life Center/Parking Lot Renovation Project - Design Build Construction Manager $4,000,000.00
Design & Construction Project Manager Faith Christian Fellowship - Owings Mills, MD
- $7 Million Dollar 15,000 sq. ft. -Sanctuary/Gymnasium Office & Classroom Facility
Emila Acrogymnastics Training Center - Laurel, MD
Conceptual 76 KW rooftop Solar system and Silicon Spray Applied Roof repair. $600,000.00
Woodlawn Senior High School - Woodlawn, MD
- 1800 Seat Football Grandstand $400,000.00 Concrete Pillars, Footings, Steps, Sidewalks, Steel Framing, aluminum seating, Electrical Conduit Borings, Electronic Score Board, Press Box installation
Derrick A. Burnett 443.985.0742 C4bmore1@gmail.com
AEI -Design Build LLC. General Contractor - Project Manager -Cont’d)
Milford Mill High School - Baltimore, MD
- 800 Seat Football Grandstand Project $250.000.00 Concrete Pillars, Footings, Steps, Sidewalks, Steel Framing, aluminum seating , Electrical Conduit Borings, Electronic Score Board , Press Box installation
Randallstown High School - Randallstown, Maryland
- 800 Seat Football Grandstand Concrete Pillars, Footings, Steps, Sidewalks, Steel Framing, aluminum seating, Electrical Conduit Borings, Electronic Score Board, Press Box installation $250,000.00
Baltimore City Public Schools - Baltimore, MD
- Energy Performance Contract Project $15,000,000.00 Supervised (4) on site project engineers to execute projects. (22) School projects, replaced, Renewable Energy Components consisting of the following components: Rooftop HVAC units, boilers, chillers, exchanged lighting fixtures and ballast, windows, and exterior doors.