Mach 30 IPT Meeting May 10, 2016
Discussion Topic: Sprint 2 Planning
Attending: J, Ray, Aaron, Greg, Brian
Start: 2040 Eastern
End: 2120 Eastern
Summary:
Planned Sprint 2 with a goal of capturing weather satellite images and wrapping up documentation for link budget while continuing to promote Ground Sphere
Minutes:
Link to backlog
- Did -
- Will do -
- Blocked? -
- Pre-planning Stand Up/Review
- Did - ENG-14 (fix svn for GS3) is done (demo’ed)
Done accepted by Greg - Will do - n/a
- Blocked? - none
- Did - ENG-09 (paper link budget vs selected spreadsheet); calculations look great
Done not quite accepted - J would like to see the PDFs uploaded and the wiki content updated from the minutes - Will do - n/a
- Blocked? - installing tools on new laptop
- Did - MKTG-25a (translate the logo to a version that can be embroidered); did research and then reduced the number of colors to seven and then digitized it into embroidery path (using free trial tool); need to upload the design still
Done accepted with the understanding that Ray will upload all materials to ODE tonight
-- Brian knows a place that might be able to help move to production from this PBI - Will do - n/a
- Blocked? - none
- Sprint planning - see backlog
- Sprint Team members for Sprint 2
- J, Brian, Aaron (light capacity)
- Sprint 2 pre-week 1 commitments
- J - wiki updates for ENG-09
- Aaron - upload PDFs for ENG-09
- Brian - MKTG-26 and week 1 of MKTG-27