Post Break Meeting (01/26/2016 1600-1715)

Reviewing Break Work                                                (1600-1745)

Week 0 *

1/24-1/30

Week 1 *

1/31-2/6

Week 2

2/7-2/13

Week 3 *

2/14 - 2/20

  • AD-03
  • AD-10
  • ST-08
  • AD-21
  • EM-07
  • ST-09
  • Deliverable
  • Gantt chart
  • Testing
  • Review Designs
  • Notifications
  • N-01
  • N-06
  • Buffer Week, finish earlier, incomplete requirements
  • ST-08 Done

Week 4

2/21-2/27

Week 5 *

2/28 - 3/5

Week 6

3/6-3/12

Week 7 *

3/13 - 3/19

  • AD-12 -templ.
  • AD-13 -templ.
  • N-02 -time
  • N-03 -time
  • N-08
  • N-04
  • N-07
  • R-01
  • R-02
  • AD-16
  • R-04

Week 8

3/20-3/26

Week 9 *

Expectation Setting

3/27 - 4/2

Week 10

4/3-4/9

Week 11 *

4/10 - 4/16

Spring Break

(Woo)

  • R-15
  • R-16

BUFFER

  • O-01 (Check)

Feature Freeze

Go/NoGo

Metrics to be added to the project as a result of this meeting:

Requirement Volatility as a result of this meeting:

  1. AD-12 - added “templates” after notifications