Mach 30 #EngineerSpeak Hangout Oct 29, 2015
Discussion Topic: Sprint 3 Stand Up 3
Attending: J, Aaron, Chris, Jeremy
Start: 2200 Eastern
End: 2255 Eastern
Summary:
Progress on Sprint 3 continues apace and Jeremy has freed up and will be joining the team for the back half of Sprint 3, primarily working on verification of the test geometry for Yavin
Minutes:
- Did - not assigned work: drafted blog post re: OSHW and The Martian that includes references MTK and met with PSAS (I saw their 3D printed Cold Gas Thruster!)
- Will do - start work on MTK wiki and landing page (for real) and sharing PSAS materials on Yavin forums/wiki
- Blocks? - this week was on crazy travel and got pulled into blog work; no travel for next 10 days or so
- Did - updated all the minutes links for Yavin (except sprint 2 stand up 4 which is missing), has not done MTK yet
- Will do - MTK minutes updates
- Blocks? - none
- Did - been trying to fix a bug in Python Markdown extension that is very frustrating as it makes the notebooks fail randomly (not quite block level), went ahead and but got it reportable (with proposed patch) while it was fresh;
- Will do - get back to the unit test PBI and if needed respond to the ticket reported to the extension team
- Blocks? - none
- clarified YVN-10 is about merging unit tests of the pressure vessel class with the documentation of that class
- adding a PBI to demo unit testing the geometry for YVN to start practicing geometry verification
- Jeremy - willing to take on the new PBI (YVN-22)
- Chris - can Jeremy finish this PBI in the next 3 weeks?
- Jeremy - yes
- Chris - then ok to add it to the sprint
- J - so Jeremy is in the sprint and is committing to YVN-22?
- Jeremy - yes