Mach 30 #EngineerSpeak Hangout June 11, 2015
Discussion Topic: Sprint 1 Stand Up 5
Attending: J, Aaron, Jeremy, Ethan
Start: 2210 Eastern
End: 0010 Eastern
Minutes:
- Did - reviewed the EC Review with the ECTF (Matt), Matt indicated that the EC Review for Yavin is complete; claiming done on this PBI
- Will do -
- Blocks? - n/a
- Did - Completed first three sections (Requirements, Theory, Implementation) and updated local build of MTK to support line wrapping of included source code
- Will do - Tests (have a plan for selecting 9 test cases and have already included the required code to support using Pint in the MTK document)
- Blocks? - none
- Did - was supposed to integrate Pint into the CAD model and clean up the code some more; but did not get these done
- Will do - integrate pint and the python library into the cad model to get to done (dropping code clean up)
- Blocks? - would be good to pair program some of this, need to know when J is available
- Did -
- Will do -
- Blocks? -
- <J and Jeremy pair programmed and integrated Pint and the python library into the CAD model and exported an STL of the hello world chamber - can claim done on CAD part of the PBI>