SUBJECT: June 10 - Solarize Plano Project Communications Update
School is out! Summer has arrived! What better time to learn more and sign up for solar energy!.
**** To review this and prior Project Communications, go to the URL below ***** http://www.solarizeplano.org/p/communications.html
This project status email is being sent to 2014 Solarize Plano Project participants that have enrolled, interested volunteers, the selected solar installation company, and related city & utility staff contacts . This communications update includes:
1. Phase 2 underway!
2. Next Steps
3. Need an in-person Information Meeting?
4. Overall enrollment project statistics
5. Project Questions
1. Phase 2 underway!
There are about 5 more weeks for Phase 2 enrollment. Tell others! Help spread the word about the 2014 Solarize Plano Project! Send them to www.solarizeplano.org to learn more and enroll!
2. Next Steps
Once enrolled, if you haven't already participated in one of the Information Sessions or watched the online videos - see Schedules and Presentations
If you are ready for Decision Point 2 (DP2), please don’t delay completing the 2014 Decision Point 2 Form Questionnaire. The sooner we have your DP2 response, the sooner your site assessment can be scheduled and a proposal can be prepared for your consideration. The available Oncor incentive funds are continuing to be used up, so the sooner you make a decision, the better your chances that Oncor incentive funding will still be available.
3. Need an in-person Information Meeting?
With all of our Information Session Meetings now available online (see Schedules and Presentations), we were not planning to hold additional “in-person” Information Session meetings. However, if you think it would be beneficial for you, please respond to this status update email to let us know. If we find that 10+ people would like another in-person session, we will try to get one scheduled.
4. Overall enrollment project statistics (as of June 9)
Phase 1 | Total (including Phase 2) | |
# of Plano enrollees | 132 | 155 |
# of DP2 yes/maybe | 35 | 41 |
# of site assessments completed | 32 | 35 |
# of proposals submitted to enrollees | 32 | 35 |
# of contracts committed by enrollees | 15 (83.3 kW) | 16 (89.4 kW) |
# of Phase 1 installations started (planned late June) | tbd | n/a |
# of Phase 1 installations completed (expected late August) | tbd | n/a |
# of Phase 2 installations started (planned early Sept) | n/a | tbd |
# of Phase 2 installations completed | n/a | tbd |
5. Project Questions
If you have any questions, please reach out to us by email so that we can setup a call or meeting to address them.
Thanks again for your interest in the Solarize Plano Project and tapping the local solar energy that we have here in Plano!
Shine On!
Larry Howe (rlhowejr@gmail.com) , Bob Litwins (rlitwins@gmail.com), and all the volunteers with Plano Solar Advocates, a 100% grassroots volunteer group
**** To review this and prior Project Communications, go to the URL below ***** http://www.solarizeplano.org/p/communications.html