Blue Valley Bond 2023 Timeline (Accessible Version)
Updated automatically every 5 minutes
Blue Valley Bond 2023
Middle School #11
2024
January to July - Design
August to September - Bidding
October to December - Construction
2025
January to December - Construction
2026
January to April - Construction
Leawood Elementary Mobile Removal and Addition
2024
January to July - Design
August - Bidding
September to October - Planning
November to December - Construction
2025
January to April - Construction
Hilltop Early Childhood Center Expansion
2024
January to April - Design
March to June - Bidding
July - Planning
August to December- Construction
Cedar Hills Elementary Mobile Removal and Addition
2024
January to July - Design
August to September - Bidding
October - Planning
November to December - Construction
2025
January to April - Construction
Performing Arts Addition at Blue Valley North
2024
January to August - Design
September - Bidding
October to November - Planning
December- Construction
2025
January to July - Construction
Career and Technical Education Upgrades at High Schools
2024
September to December  - Design
2025
January - Design
February- Bidding
March to May- Planning
June to July- Construction
August to December- Planning
2026
January to May- Planning
June to July- Construction
Blue Valley North P.E. and Athletics Addition and Renovation
2024
January to February - Design
March- Bidding
April to May - Planning
June to December- Construction
2025
January to December - Construction
Blue Valley West Aux Gym Addition
2024
January - Bidding
February to May - Planning
June to December - Construction
2025
January to March - Construction
Harmony Middle School Multipurpose Addition
2024
February to June - Design
June to July - Bidding
August to October - Planning
November to December- Construction
2025
January to July - Construction
Blue Valley Northwest P.E. and Athletics Addition and Renovation
2024
February to June- Design
June to August - Bidding
August to October - Planning
November to December- Construction
2025
January to May - Construction
Blue Valley High P.E. and Athletics Addition and Renovation
2024
February to March - Design
2025
March to June - Design
July to August - Bidding
September to November- Planning
December- Construction
2026
January to July- Construction
Pleasant Ridge Middle School Multipurpose
2024
February to March - Design
July to October- Design
November to December- Bidding
2025
January to March- Planning
April to December- Construction
Blue Valley Southwest Aux Gym Addition
2024
December- Design
2025
January to March - Design
April to May- Bidding
June to August- Planning
September to December- Construction
2026
January to June - Construction