Campus Building Electrical Shutdowns for this weekend and the week of August 15
Friday, August 12
Time: 6 p.m. to 2 a.m. Saturday, August 13
Road: Barstow Avenue - Maple to Chestnut
Buildings: Student Recreation Center, Save Mart Center
Time: 6 p.m. to 10 p.m.
Buildings: Grosse IT towers
Time: 6 p.m. to 6 a.m. Saturday, August 13
Buildings: Engineering West
Time: 10 p.m. to 10 a.m. Saturday, August 13
Buildings: Smittcamp Alumni House, University High School, Student Recreation Center, Save Mart Center
Wednesday, August 17
Time: 5 p.m. to 7 a.m. Thursday, August 18
Buildings: Keats
Thursday, August 18
Time: 6 p.m. to 2 a.m. Friday, August 19
Buildings: McKee Fisk, East Side
Friday, August 19
Time: 6 p.m. to 8 a.m. Saturday, August 20
Buildings: Grosse IT Towers
Time: 10 p.m. to 1 p.m. Saturday, August 20
Buildings: Kremen, Peters Business, Music Addition
Note: Joyal Parking Lot will be open for parking on Monday August 15th.
Closed Areas on Campus
Central Quad Area between the Social Science, McKee Fisk, Professional Human Services and Family & Food Science buildings will be closed to pedestrian and vehicle access starting Monday, July 18th due to reconstruction of this area. Thank you for your patience as we work to improve the aesthetics of this highly used area. Access to these buildings during construction will not be impacted. Click HERE for path of travel and site plan.
Barricades and signage to redirect vehicle and pedestrian traffic will be displayed throughout construction areas.