Capstone - Schedule of activities for summer'08
Weeks
| Date
| Activity due
|
Week 1
| June 2nd
| - selection of your medium for publishing you e-portfolio
- project proposal
|
Week 2
| June 9th
| - scan and collection of sample of works (e-portfolio)
- abstract and initial outline (project)
|
Week 3
| June 16th
| - update of your CV and plan for e-portfolio design
- bibliography and revised outline
|
Week 4
| June 23rd
| - thoughts of your summative reflection
|
Week 5
| June 30th
| - draft of the e-portfolio / final version of the summative statement
- literature review (one section of the project) and revised outline of the project with more detail
|
Week 6
| July 7th
| - initial reflection of sample of works and courses (e-portfolio)
|
Week 7
| July 14th
| - 2nd draft of e-portfolio for feedback
|
Week 8
| July 21st
| - draft version 1 (project)
|
Week 9
| July 28th
| - full version of the e-portfolio (without appended project)
- draft version 2 (project)
|
Week 10
| August 4th
| - final version of e-portfolio
- final version project
|