Assured Labor ICT4D Team Project

Work Plan

Note: Please edit this to reflect what you want/are working on! This initial week's description of tasks is based on what we discussed in our meeting today.

Monday 3/3 - Sunday 3/9
    Katchy, Elena, and Kevin: meet with Luis or another instructor to help us kick off rapid development of the prototype (1st iteration of 2)
    Jane, Joseph: set up meeting with Assured Labor software core team, find location/setting for field test of prototype, find out how flexible they are about when a field test could be conducted (the more flexible things are, the longer we have to work on the prototype before committing ourselves to a particular field test date)

Monday 3/10 - Sunday 3/16
    Pre-Spring Break write up due Thursday 3/13

Monday 3/17 - Sunday 3/23
    Finish 1st iteration of prototype

Monday 3/24 - Sunday 3/30
    Spring Break

Monday 3/31 - Sunday 4/6
    Approximate time to test prototype in the field (Boston)

Monday 4/7 - Sunday 4/13
    Analyze field test results, feedback
    start working on 2nd iteration of prototype

Monday 4/14 - Sunday 4/20
    Post-Spring Break write up due Thursday 4/17

Monday 4/21 - Sunday 4/27

Monday 4/28 - Sunday 5/4
    Finish 2nd (final) prototype

Monday 5/5 - Sunday 5/11
    Finish paper and presentation, practice presentation

Monday 5/12 - Sunday 5/18
    Give final presentation