PMP Formulas
Edited by Venkat
|
Forward Pass ES = EF of the predecessor node EF = ES + Du Backward Pass LF = LS of the Successor LS = LF – Du |
ES Du EF
Node
LS Float LF
ES Du EF
Slack = LF – EF = LS – ES
Free Float = ES(Successor) - EF(Predecessor) |
|
Q U A L I T Y |
|
|
CoQ = ( ( Review Efforts + Test Efforts + Training Efforts + Rework Efforts + Efforts of Prevention) / Total Efforts) x 100 % PERT = O + 4ML + P 6 |
MEAN Average MODE The “most found” number RANGE Largest - Smallest Measure. MEDIUM No in the middle or avg. of 2 middle Nos |
|
STD. DEV. OF TASK = P - O 6
T 6 ____________ CP STD. DEV. = √ σ² + σ² + σ² |
SIGMA 1 = 68.26 2 = 95.46 3 = 99.73 6 = 99.99
Channels of Communication |
|
P R O J E C T S E L E C T I O N |
|
|
PV = F V . (1+r)ⁿ FV = PV x (1+r) NPV = ( PV + PV + PV + PV ) (1+r)ⁿ (1+r)ⁿ (1+r)ⁿ (1+r)ⁿ |
Cash Flow = Cash Inflow – Cash Outflow Discounted Cash Flow = CF x Discount Factor ARR = Cash Flow / No. of Years ROI = (ARR / Investment) * 100 % BCR = Benefits / Cost Exp. Value = Probability % x Consequence $ |
|
Class of Estimates |
Contract Incentives |
|
E A R N E D V A L U E A N A L Y S I S |
|
|
PV (Present Value) = BCWS (Budgeted Cost of Work Schedule) EV (Earned Value) = BCWP (Budgeted Cost of Work Performed) AC (Actual Cost) = ACWP (Actual Cost of Work Performed) |
|
CV = EV – ACCPI = EV / AC (efficiency) SV = EV – PV SPI = EV / PV |
ETC = BAC – EV or (BAC – EV) / CPIEAC = AC + ETCEAC = BAC / CPIVAC = BAC – EAC |
|
% COMPLETE = EV / BAC x 100 % SPENT = AC / BAC x 100 |
CV% = AC / EV x 100 SV% = AC / PV x 100 |
Page 1 of 1